问卷申请的项目估算计划 [英] Project Estimate plan for a Questionaire application

查看:59
本文介绍了问卷申请的项目估算计划的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

嗨 我想创建一个Questionaire应用程序,这是一种用于在线购物车网站的网络调查应用程序.我需要为任务创建一个估计.您能帮我为问卷或网络调查类型的应用程序提供示例估算计划吗?感谢您的帮助.

问候,
Usha

Hi I wanted to create a Questionaire application which is a web survey application kind for an online shopping cart site. I need to create an estimate for the tasks. Can you please help me to provide a sample estimate plan for a questionaire or web survey kind of application. Thanks for your help.

Regards,
Usha

推荐答案

能否帮助我为问卷调查或网络调查提供样本估算计划
您真的认为它可以推广吗?

此外,估计是因人而异的.

我的建议:
1.整理应用程序的功能-多少个问题,屏幕,工作流程等
2.将您的项目分为几个小部分,可以将它们视为一项完整的小任务
3.估算任务时间并按您的要求进行工作&开发人员的知识.
4.为计划中的工作留一些缓冲,以处理一些遗漏/无法预见的功能/故障
5.保留一些时间进行返工

我猜想,这必须足够.尝试!
Can you please help me to provide a sample estimate plan for a questionaire or web survey
Do you really think that it can be generalized?

Further, estimation is something which would vary from person to person.

My suggestions:
1. Collate the features of your application - How many questions, screens, workflow, etc
2. Divide your project into small parts that they can be considered one complete small task
3. Estimate the task time and work as per you & the developer''s knowledge.
4. Keep some buffer for the planned work to handle some missed/unforseen feature/trouble
5. Keep some time for re-work

I guess, for a start this must be enough. Try!


不可能.您对时间估计的信心越少,预期完成任务的实时时间就越多.例如,如果您说我完全不知道我需要多少时间",那么具有相当好的有效性的估计将是永远" :-).

对于这样的估计,CodeProject成员只是错误的人.对开发人员的技能有想法的人只能给出这样的估计.在所有评论和修复之后,开发人员完成首次任务后,我通常都知道一个很好的答案.差异开发人员性能差异的一个常见想法是:大约10倍. (我不算那些无法完成工作的人.)

—SA
Impossible. The less you''re confident about the time estimate, the more the real time expected to complete the task. For example, if you say "I have no idea at all how much time I need", an estimate with reasonably good validity would be "forever" :-).

CodeProject members are just wrong people for estimates like that. Someone who has an idea of the developer''s skills can only give such estimate. I usually know pretty good answer after a developer completes first assignment, after all reviews and fixes. A common idea of the difference in performance of difference developers is: about 10 times. (I don''t count those unable to complete the work.)

—SA