Microsoft Project Server 2010中的时间表 [英] Timesheets in Microsoft Project Server 2010

查看:109
本文介绍了Microsoft Project Server 2010中的时间表的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

我们的团队今年开始使用时间表收集所有供应商的实际工作。 一旦将时间输入PWA,处理和批准,我在查看项目专业人员的实际工作时遇到问题。  &bbsp b带有时间表经验的人是否可以帮助我解决此问题? 资源已在PWA中输入实际小时数,已保存并已提交。 时间表经理批准。 项目专业时间表中没有实际的小时数。 任何想法
或建议将不胜感激。

Our team is starting this year using timesheets for collecting actual work from all of our vendors.  I am having a problem seeing the actual work in project professional once the time has been entered into PWA, processed and approved.  Would someone with timesheet experience be able to help me with this issue?  Resource has entered actual hours in PWA, saved and submitted.  Timesheet manager approved.  No actual hours show in the project professional schedule.  Any ideas or suggestions would be appreciated.

Jan Whitehead

Jan Whitehead

推荐答案

你好Jan,

实际上你必须将时间表管理器与状态管理器区分开来。

Actually you have to differenciate the timesheet manager with the status manager.

状态管理员(谁应该是项目所有者,即项目经理)将批准提交的任务更新。一旦获得批准,它将被"推送"。项目实际工作。

Status manager (who should be the project owner, ie the project manager) will approved submitted tasks updates. Once approved, it will be "pushed" to the project actual work.

时间表经理将批准完整的资源时间表,包括行政工作。

Timesheet manager will approved the complete resource timesheet, including administrative work.

请注意,如果您激活了SEM(单项模式)在PS2010中,时间表和任务更新都是通过资源的单一操作完成的。

Note that if you activated SEM (single entry mode) in PS2010, both timesheet and task update are made from on single operation by the resource.

因此,在您的情况下,由于您正在谈论时间表管理者批准,所以通常实际不发送到项目。项目经理(状态经理)必须批准任务更新,以便在项目计划中显示实际情况。

Thus in your case, since you're talking about timesheet manager approval, it is normal that the actual is not send to the project. The project manager (status manager) must approve the task updates in order for the actuals to be shown in the project plan.

请在此处找到更多信息:

Please find more information here:

http://technet.microsoft.com/en-us/ library / gg597642(v = office.14).aspx

希望这会有所帮助。


这篇关于Microsoft Project Server 2010中的时间表的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!