使用CSOM设置前任的前导/滞后 [英] Setting Lead / Lag on a predecessor using CSOM
问题描述
我想使用CSOM代码在任务2上设置前置任务。前一个是"1FS + 10days"
I want to set a Predecessor on Task 2 using CSOM code. The predecessor is "1FS + 10days"
我目前卡住了,因为我找不到任何设置"提前期"的方法。使用CSOM。
I am currently stuck as i can't find any way of setting "Lead time" using CSOM.
这是关于DraftTaskLink类的MSDN页面
This is page from MSDN on DraftTaskLink Class
http://msdn.microsoft.com/en-us/library /microsoft.projectserver.client.drafttasklink_di_pj14mref_members(v = office.15).aspx
http://msdn.microsoft.com/en-us/library/microsoft.projectserver.client.drafttasklink_di_pj14mref_members(v=office.15).aspx
另一方面,似乎有可能(虽然不太确定)通过PSI
On the other hand, it seems possible (not too sure though) through PSI
http://msdn.microsoft.com/en-us/library/websvcproject.projectdataset.dependencyrow_di_pj14mref_members(v = office.15).aspx
http://msdn.microsoft.com/en-us/library/websvcproject.projectdataset.dependencyrow_di_pj14mref_members(v=office.15).aspx
这是一个限制吗CSOM?如果有的话,是否有专门提及此的文件?
Is this a limitation of CSOM ? If so, is there a documentation which specifically mention this ?
Hammad Arif EPM建议博客
Hammad Arif EPM Advice Blog
推荐答案
好奇,如果你有任何地方有这个。我不是试图设置这些值,但我试图获得它们并且似乎没有办法。通过PSI可以实现CSOM解决方案。
Curious if you ever got anywhere with this. I'm not trying to set these values, but I am trying to obtain them and there doesn't seem to be a way. It is possible through PSI, need a CSOM solution.