问题描述

最近我的项目不再考虑前辈了。 我正在添加一个带有finsh的任务来启动前任,并且约束是尽快但是在前任完成后没有安排任务,而是
它总是默认为项目开始日期。 什么可能导致前辈被忽略?

解决方案

Hello Mary,


首先,你让我猜猜你正在使用的版本,所以也许你不会识别一些菜单名称。我给你2010版的路径。


有两种可能性。


1。转到文件菜单,选项,计划,每次编辑后查找Calclation。如果已关闭,请将其设置为开启。


如果问题仍未解决,请逐个删除与摘要任务之间的链接,直到问题消失为止。


问候,


Recently my projects are no longer taking into account the predecessors.  I am adding a task with a finsh to start predecessor and the constraint is as soon as possible but the task is not being scheduled after the predecessor is finished, rather it is always defaulting to the project start date.  What could cause the predecessors to be ignored?

解决方案

Hello Mary,

First, you make me guess which version you are using, so maybe you will not recognize some menu names. I give you the paths for the 2010 version.

There are two possibilities.

1. Go to File menu, Options, Schedule, look for Calclation after each edit. If it's off, set it on.

If the problem isn't solved, delete one by one links to and from summary tasks until the problem disappears.

Greetings,