问题描述

我的项目中有3个任务:  Task1,Task2,Task3。现在我想在Task2中插入子任务,即Task2.1。

I am having 3 tasks in my project : Task1,Task2,Task3. Now I want to insert subtask in Task2 i.e., Task2.1.

为此,我将  TASK_OUTLINE_LEVEL的值设置为2,然后将TASK_OUTLINE_NUM设置为2.1,并将Task2的任务ID设置为父ID但仍然将任务插入Task3,其父ID将更改为Task3的任务ID,并且TASK_OUTLINE_NUM
将更改为3.1。

For this i set the values of TASK_OUTLINE_LEVEL as 2 then TASK_OUTLINE_NUM as 2.1 and also given the Task ID of Task2 as parent ID but still the task is getting inserted in Task3 and its parent ID gets changed to Task ID of Task3 and TASK_OUTLINE_NUM is getting changed to 3.1.

为什么我会出现这种行为?我做错了什么?

同样在任务数据集的项目服务器模式中,告知TASK_OUTLINE_NUM,TASK_PARENT_UID是只读的,那么如何在项目中插入任务的分层数据?  

Also in project server schema for Task dataset tells that TASK_OUTLINE_NUM,TASK_PARENT_UID are read-only so how to insert hierarchical data for task in project ? 

提前谢谢。

Ajinkya

推荐答案

你好,

你需要这样做:

newTask AddAfterTaskUID   =   taskPred ;

干杯