Project Server 2013 - 图形指示器 - 未显示在项目中心 [英] Project Server 2013 - Graphical Indicators - Not showing in the project center
问题描述
大家好,
我的要求是,我创建了一个名为项目进度
的项目自定义字段及其自定义属性公式如下
My requirement is that, I have created an Project custom field named Project Progress and its custom attribute is Formula as below
我在项目视图中添加了显示在项目中心的字段,如下所示,项目的%完成具有值,但不显示指标。
I have added the field in project view that display in the project center as below,the %complete of project having value but the indicator is not displayed.
是否有人面临同样的问题,并找到了如何在项目中心展示指标的解决方案。
Did anyone faced the same issue and found the solution how to show the indicator in project center.
提前致谢。
Sunitha
推荐答案
您好Sunitha,
Hi Sunitha,
您需要发布要计算的公式的项目以及要显示的图形指示器。
You need to publish the projects for the formula to be calculated and the graphical indicator to be displayed.
A
powershell脚本 可能有助于批量发布。
A powershell script might help by doing a bulk publish.
>
这篇关于Project Server 2013 - 图形指示器 - 未显示在项目中心的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!