我在国外有一个项目;我们派人去完成它并且他们住在现场。 

I have a project in a foreign country; we have sent men to complete it and they live on-site. 

项目日历设置为显示为期6天的工作周。 但是,我们每周向男性支付7天的费用。 

The project calendar is set up to show a 6-day working week.  However, we pay the men for 7-days per week. 

目前,Project仅在6天内应用其费用。 我需要做些什么来确定资源只工作6天,但我们付了7天?

At the moment Project is only applying their costs for the 6-day period.  What do I need to do to establish that the resources are only working a 6-day week but we are paying them for 7 days?

TIA

推荐答案

Storcktrek -

Storcktrek --

一种方法可能是提高每种资源的标准费率,以便6天的工作生成7天每种资源的总费用。 只是一个想法。 希望这会有所帮助。

One approach might be to increase the Standard Rate for each resource so that 6 days of work generates 7 days of total Cost for each resource.  Just a thought.  Hope this helps.