非工作日的成本应计 [英] Cost Accrual on Non-Working Days
问题描述
我在国外有一个项目;我们派人去完成它并且他们住在现场。
I have a project in a foreign country; we have sent men to complete it and they live on-site.
项目日历设置为显示为期6天的工作周。 但是,我们每周向男性支付7天的费用。
The project calendar is set up to show a 6-day working week. However, we pay the men for 7-days per week.
目前,Project仅在6天内应用其费用。 我需要做些什么来确定资源只工作6天,但我们付了7天?
At the moment Project is only applying their costs for the 6-day period. What do I need to do to establish that the resources are only working a 6-day week but we are paying them for 7 days?
TIA
推荐答案
Storcktrek -
Storcktrek --
一种方法可能是提高每种资源的标准费率,以便6天的工作生成7天每种资源的总费用。 只是一个想法。 希望这会有所帮助。
One approach might be to increase the Standard Rate for each resource so that 6 days of work generates 7 days of total Cost for each resource. Just a thought. Hope this helps.
这篇关于非工作日的成本应计的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!