问题描述

大家好,

我创建了一个时间表 模板并将其附加到项目类型。

I have created a schedule template and attached it to projec type.

现在为每个项目创建通过PM,计划将根据计划模板自动创建并可用。

Now for every project created by the PM's, the schedule is getting automatically created and available as per the schedule template.

但问题是状态管理器显示为我的名字(管理员)而不是PM名称。

But the problem is the Status Manager is showing as my name (administrator) and not the PM name.

这是一个已知问题吗?任何人都可以告诉我改变所有项目的状态管理器(大约有400个项目)或PSI程序,这将改变项目的状态管理器,所以我可以循环并更新项目。

Is it a known issue? Can anyone tell me a work around to change the status manager for all projects (there are around 400 projects) or PSI program which will change status manager for a project, so i can loop through and update a project.

请帮助它非常紧急和生产:(

Please help its very urgent and on production :(



谢谢&Regards

Ravishankar Polepalli(MCP,MCC)

Microsoft Dynamics,Project Server和SharePoint Server顾问

ravi.polepalli@gmail.com


Thanks & Regards
Ravishankar Polepalli (MCP,MCC)
Microsoft Dynamics, Project Server and SharePoint Server Consultant
ravi.polepalli@gmail.com

推荐答案

嗨Ravishankar,

Hi Ravishankar,

一种可能的解决方法是在VBA中编写一个宏

A possible workaround is to write a macro in VBA that


  • 通过SQL读取项目列表
  • 循环项目列表
  • 打开项目
  • 循环任务和更新状态管理器( ActiveProject.Tasks(i).StatusManagerName = NewStatusManager)
  • 保存和/或发布项目
  • 关闭并打开下一个项目

使用这样的解决方案,您可以轻松实现流程自动化。

With a solution like this you can automate the process easily.