问题描述

我们将在线使用资源管理项目 - 在许多机器上管理工作负载 - 并在整个团队中协同执行此功能。


我想知道如何管理资源在线项目。在我的资源/机器上加载任务之后,我需要能够查看/查看在这些资源/机器上分配了多少工作负载,以及是否可以将未决任务分配给资源或者随后解决
。 / p>

我想使用2个项目专业版和2个项目精简版许可来管理资源/机器。

解决方案

msayani2 -


首先,您需要在企业资源库中输入所有人员和计算机。  对于您列出的每台机器,输入最大值。单位值代表100%乘以您拥有的机器数量。  例如,如果你有
三个道路评分者,你将在Max中输入300%。 Road Grader资源的Units列。


接下来,您需要构建企业项目,在项目中添加所需的人员和机器作为团队成员,根据需要为每个任务分配资源然后保存并发布每个企业项目。


要查看资源的工作负载分配方式,请导航到"资源中心"页面,然后选择要分配其分配和可用性的资源。 。  在"资源"功能区的右端,单击"资源可用性
"按钮。  在资源可用性上,选择您要使用的时间范围,然后您可以查看所选资源的可用性。  您还可以单击"资源分配"按钮,研究如何在Project Server中的所有项目中使用资源


希望这会有所帮助。


We will be using project online for Resource Management - managing the workload on many machines - and do this function across the team collaboratively.

I was wondering how resources are managed in Project online. After loading tasks on my resources/machines , I need to be able to see/view how much workload is distributed on these resources/machines and if I can assign a pending task to the resource or shuffle the work around.

I would like to use 2 project pro and 2 project lite licenses to manage resources/machines.

解决方案

msayani2 --

Firstly, all of your people and machines need to b entered in the Enterprise Resource Pool.  For each of the machines you list, enter a Max. Units value that represents 100% multiplied by the number of machines you have.  For example, if you have three road graders, you would enter 300% in the Max. Units column for a Road Grader resource.

Next, you will need to build enterprise projects, add the required people and machines as team members in the project, assign the resources to each task as needed, and then save and publish each enterprise project.

To see how the workload is distributed for your resources, navigate to the Resource Center page and select the resources whose assignments and availability you want to study.  At the right end of the Resources ribbon, click the Resource Availability button.  On the Resource Availability, select the time range you want to use and you can then see the availability of your selected resources.  You can also click the Resource Assignments button to study how the resources are being used on tasks across all projects in Project Server.

Hope this helps.