Visual Studio - 交付计划 [英] Visual Studio - Delivery Plan

查看:84
本文介绍了Visual Studio - 交付计划的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

Visual Studio中的交付计划的问题/问题

Questions/Issues with Delivery Plan in Visual Studio's

1。如何在不必点击它们的情况下显示交付计划中的标记名称?这样当用户进入该页面时它们会显示?  

1. How can you get the names of the markers in the Delivery Plans to display without having to click on them?So they display when a user get's to that page?  

2。你怎么能把卡片从Kanbon板上拉到交付计划中?根据我的研究,这两个应该互动?如果它们不是交互式的,您如何在交付计划中创建新的记事卡?

2. How can you pull in the cards from the Kanbon board into the delivery plan? According to my research, these two should be interactive? If they are not interactive, how can you create new note cards in the delivery plans?

请联系我以获取截屏。我尝试附加图片,但收到错误后我才能验证我的帐户?

Please contact me for screen shots. I tried to attach images, but received an error I am unable to until you verify my account? 

谢谢你,

pmf4287

推荐答案

嗨pmf4287,

Hi pmf4287,

谢谢你伸出援手。对于Markers,我们无法在没有点击激活的情况下显示标记。我们最初的设计选择是避免噪音,所以我们点击后就可以使用它们。我理解您对
选项的反馈配置。

Thank you for reaching out. For Markers, we do not have the capability to display the Markers without a click to activate yet. Our initial design choice was to avoid noise, so we made them available upon click. I understand your feedback for an option to configure this.

交付计划基于迭代路径,因为我们根据预期交付/发运的sprint在日历元素上渲染工作。对于此版本,如果看板团队想要利用计划,他们将不得不选择在项目中定义的迭代/冲刺
,并将工作分配到适当的迭代路径中。

The Delivery Plan is based on the iteration path because we render work on a calendar element based on the sprint it is expected to be delivered/shipped. For this version, if Kanban teams want to leverage Plans, they will have to opt into the iterations/sprints defined in their project and assign work into the appropriate iteration paths.

如果您有任何其他问题,请再次联系。

Please reach out again if you have any other questions.

最好,

Sondra Batbold

Sondra Batbold


这篇关于Visual Studio - 交付计划的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!