如何进行流平,以便在资源完成之前永远不会将资源分配给另一个任务(将资源粘贴到单个任务上直到完成)? [英] How to costrain leveling so that a resource is never assigned to another task until its current one is finished (stick resources to a single task until it is finished) ?

查看:86
本文介绍了如何进行流平,以便在资源完成之前永远不会将资源分配给另一个任务(将资源粘贴到单个任务上直到完成)?的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

您好,¥b $ b我对资源分配和自动调平功能感到困惑。


如果我将资源分配给2个任务没有链接在一起(即它们确实在同一天开始),当练级项目(专业2013)对资源进行精确调整,使其在第一个任务上工作5个小时,在第二个任务上工作3个。


如你所知,你不能每天都有人从一个任务转移到另一个任务,因此我想要实现的是,由于分配,资源永远不会在两个任务之间分配,而是其中一个任务被延迟,直到资源完成
其他任务。

我希望项目考虑资源"粘性"。任务完成之前的任务。


我如何实现这一目标?



谢谢提前

解决方案

将任务的优先级设置为超过默认值500(例如设置为700左右),您要完成首先是资源。现在,当您进行级别时,项目将考虑该任务的优先级,以将低优先级任务转移到以后的日期。


http://office.microsoft.com/en-in/project-help/set-task-priorities-for-资源调配-HA102840083.aspx


http://office.microsoft.com/en-in/project-help/about-resource-leveling-HP001041939.aspx


Hello,
I am really puzzled with the resource assignments and auto-leveling feature.

If I assign a resource to 2 tasks which are not linked together (i.e. they do start at the same day), when levelling project (professional 2013) tipically levels the resource so that it works 5 hours on the first task and the remaining 3 on the second one.

As you know you can't move someone from a task to another every day, thus what I want to achieve is that, due to the assignment, the resource is never split between the two tasks, but rather that one of the task is delayed until the resource finishes the other task.
I want project to consider a resource "sticky" to a task until the task is completed.

How can I achieve this?

Thanks in advance

解决方案

Set the priority of the task more than default 500, (say set to 700 or so)which you want to be completed first by the resource. Now when you level, project will consider the priority of that task to shift the low priority task to later date.

http://office.microsoft.com/en-in/project-help/set-task-priorities-for-resource-leveling-HA102840083.aspx

http://office.microsoft.com/en-in/project-help/about-resource-leveling-HP001041939.aspx