问题描述

大家好,

我是MS Project的新手。我们正在从excel转向MS Project。我们希望能够跟踪施工现场的人力数量,例如:

Hi all,
I'm new to MS Project. We're moving from excel to MS Project. We would like to be able to track number of manpower in our construction site, for example:

任务 SMTWTFS

挖掘 0 2 2  2 2 2 2

形成 0 2 4  3 2 2 2
$
钢筋 0 3 2  2 3 2 1

Task S M T W T F S
Excavation 0 2 2  2 2 2 2
Forming 0 2 4  3 2 2 2
Rebar 0 3 2  2 3 2 1

上面的数字代表在任何一天工作的总人工数量。以前我们使用excel表跟踪总计数,但我很难在MS Project中找出它。

The numbers above represent total labour count working in any given day. Previously we tracked total count using excel sheet but i'm having a hard time figuring it out in MS Project.

任何人都可以帮我这个吗?

Anyone can help me with this?

谢谢。

推荐答案

bApTizE -

bApTizE --

在您的资源工作表视图中项目,输入您的工人类型的名称。 您可以输入这些工作人员的真实姓名,也可以输入角色名称。 如果输入角色,例如Laborer,则输入Max。单位列,
输入您拥有该类型的工人数量的100%倍。 例如,如果有12名工人可以使用该项目,请在Max中输入1200%。单位字段。

In the Resource Sheet view of your project, enter the names of the types of your workers.  You can enter the real name for those workers, or you can enter the names of roles.  If you enter roles, such as Laborer, then in the Max. Units column, enter 100% times the numbers of workers you have of that type.  For example, if you have 12 laborers available to work on the project, enter 1200% in the Max. Units field.

在"甘特图"视图中,确保在每个任务的"持续时间"列中输入了持续时间估计值。 右键单击"甘特图"视图的右半部分中的"甘特图"窗格中的任意位置,然后在快捷菜单上选择"显示拆分"。 
在顶部窗格(甘特图窗格)中选择任务。 在底部窗格(任务表单窗格)中,首先选择处理任务的资源的名称,每行一个资源,但不要在顶部窗格中单击,也不要单击"确定"按钮。 如果
输入人名,请在每个人的"单位"列中输入100%。 如果输入角色的名称(例如Laborer),请输入该类型的工作人员数量的100%倍。 因此,如果您要在任务中使用4名工人,请在
单位列中输入400%。 完成选择将处理该任务的所有资源后,单击底部窗格中的"确定"按钮。 您将看到Microsoft Project计算任务中每个人或角色的工作。

In the Gantt Chart view, make sure that you entered a duration estimate in the Duration column for each task.  Right-click anywhere in the Gantt Chart pane in the right half of the Gantt Chart view and select Show Split on the shortcut menu.  Select a task in the top pane (Gantt Chart pane).  In the bottom pane (Task Form pane), first select the names of the resources working on the task, one resource per row, but DO NOT click in the top pane and DO NOT click the OK button yet.  If you enter the names of humans, enter 100% in the Units column for each human.  If you enter the name of a role, such as Laborer, enter 100% times the number of workers of that type.  So, if you are going to use 4 laborers on the task, enter 400% in the Units column.  When finished selecting all of the resources who will work on the task, click the OK button in the bottom pane.  You will see that Microsoft Project calculates the Work for each person or role on the task.

在底部窗格中,有一个名为Effort Driven的复选框选项。 如果选择此选项并在以后向此任务添加帮助程序,Microsoft Project将自动缩短任务的持续时间,因为更多工作​​人员正在共享
工作负载。 如果这是您要执行此任务的行为,请保持选中该选项。 如果这不是您想要的行为,请取消选中"努力驱动"复选框,然后单击底部窗格中的"确定"按钮。

In the bottom pane, there is a checkbox option called Effort Driven.  If this option is selected and you add helpers to this task at a later time, Microsoft Project will automatically shorten the Duration of the task because more workers are sharing the workload.  If this is the behavior you want for this task, leave the option selected.  If this is NOT the behavior you want, DESELECT the Effort Driven checkbox and then click the OK button in the bottom pane.

这些是一些让您朝着正确的方向前进的想法 希望这会有所帮助。

These are some ideas for you to get you moving in the right direction.  Hope this helps.