问题描述

我想PSI直接更改Assignment的完成百分比,直接从Published library里面更改视图来改变结果,项目经理不需要批准这个更改以及怎么做?

I want to the PSI directly change the percentage of completion of the Assignment, changes directly from Published library inside view to change the results, the project manager is not required to approve this change and how to do it?

推荐答案

你好 -

建议下载ProjTool应用程序&查看代码:

http://blogs.msdn.com/b/project_programmability/archive/2010/11/03/projtool-for-project-server-2010.aspx

Would suggest to download the ProjTool application & look into the code:
http://blogs.msdn.com/b/project_programmability/archive/2010/11/03/projtool-for-project-server-2010.aspx

请参阅以下部分:  修改项目数据

http://msdn.microsoft.com/en-us/library/office/gg446880 (v = office.14).aspx

See the section: Modifying Project Data
http://msdn.microsoft.com/en-us/library/office/gg446880(v=office.14).aspx

HTH,


这篇关于更改作业完成的百分比的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!