项目详情页面:'时间表' [英] Project Detail Page: 'Schedule '

查看:56
本文介绍了项目详情页面:'时间表'的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

大家好,

我正在尝试使用"计划"项目详细信息页面中的"手动计划"和"自动计划"功能。我通过项目中心访问此项目。

I am trying to use the feature 'Manually Schedule' and 'Auto Schedule' in the 'Schedule' Project Detail Page. I am accessing this via Project Centre.

问题是此功能是灰色的,还有"完成百分比"。特征。 "服务器设置"中的"任务模式设置"中没有任何内容导致此问题。

The issue is that this feature is greyed out and also the "Percentage Complete" feature. There is nothing in the 'Task Mode Settings' in 'Server Settings' that is causing this issue.

如果我使用Project Professional 2010访问相同的时间表,那么它可以正常工作。

If I access the same schedule using Project Professional 2010, then it works fine.

有没有人知道是否有其他设置我可能错过了"开启" "计划项目详细信息页面"中的此功能?

Does anyone know if there is another setting that I may have missed out to "switch-on" this feature in 'Schedule Project Detail Page'?

谢谢,

SJ

推荐答案

在Project Server 2010中,Schedule Web部件与Project Pro相比具有局限性。查看

http://blogs.msdn.com/b/brismith/archive/2010/09/10/project-server-2010-scheduling-on-the-web- -psi-and-project-professional.aspx


http://www.microsoft.com/project/en-us/project-server-2010-editions.aspx
了解更多详情。
In Project Server 2010, the Schedule web part has limitations compared with Project Pro. Check out http://blogs.msdn.com/b/brismith/archive/2010/09/10/project-server-2010-scheduling-on-the-web-the-psi-and-project-professional.aspx and http://www.microsoft.com/project/en-us/project-server-2010-editions.aspx for more details.


这篇关于项目详情页面:'时间表'的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!