问题描述

基本日历和资源日历之间的差异

推荐答案

您好,

基准日历是Project在三个方面使用的日历: 

A base calendar is a calendar used by Project in three areas: 

1) 作为任务日历 - 按任务分配的特定日历,用于在项目日历的正常工作时间(通常)之外安排任​​务。 例如,如果要在周末处理任务,但项目
日历将这些日期视为非工作时间,我会创建一个新的基本日历,使星期六和星期日工作 天,并打电话它是"周末工作日历"。 然后,我会将其分配给任何需要通过高级选项卡上的任务信息对话框安排在周末
的任务。  (提示:我还会选中"计划忽略资源日历"复选框)

1)  As a task calendar - a specific calendar assigned on a task-by-task basis to schedule a task outside the normal working hours (usually) of the project calendar.  For example, if a task is to be worked on the weekend but the project calendar has those days as non-working time, I would create a new base calendar, make saturday and sunday working days, and call it "Weekend Working Calendar".  I would then assign it to any task that needs to be scheduled over the weekend via the task information dialog box, on the advanced tab.  (Hint: I would also check the checkbox that says "Scheduling ignores resource calendars")

2) 作为项目日历(用于在未分配资源时安排任务或当没有分配任务日历时。)

2) As a project calendar (used to schedule tasks when no resources are assigned or when no task calendar is assigned).

3)作为资源日历的基础。 例如,假设我们在一个项目上有100个资源。 这些资源中的35个每周工作4天,每天工作10小时(有时称为"4-10")。 我将创建一个新的基本日历,输入反映工作时间的4天和时间,并将其称为"4-10日历",而不是将所有35个资源日历
更改为4天/ 10小时。 ; 然后将其指定为这35个资源的基本日历。

3) As the basis for a resource calendar.  For example, let's say we have 100 resources on a project.  35 of these resources work 4 days per week, 10 hours per day (sometimes called "4-10's").  Instead of changing all 35 resource calendars to 4 days/10 hours, I would create a new base calendar, enter the 4 days and times that reflected the working times, and call it the "4-10 Calendar".  This is then assigned as the base calendar for those 35 resources.

资源日历是Project为每个工作类型资源创建的日历,您在资源工作表中输入。 每个资源都有自己的日历,无法分配给任何任务或其他资源。 默认情况下,输入的每个资源
将在资源创建时采用项目日历。 资源日历不是为成本或物质资源创建的。

A resource calendar is a calendar created by Project for each WORK type resource you enter in the resource sheet.  Each resource has their own calendar and it cannot be assigned to any task or to another resource.  By default, each resource entered, will assume the project calendar at the time of resource creation.  Resource calendars are not created for cost or material resources.

希望这会有所帮助。