用通用资源替换实际资源 [英] Replacing real resources with generic resources

查看:78
本文介绍了用通用资源替换实际资源的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

大家好,我已经创建了一个资源加载的项目计划。 我的管理层希望将计划发送给客户,但不希望显示实际资源,而只是显示通用列表。 有没有一种简单的方法可以做到这一点? 我以为我可以
分配,比如300%利用通用名称,然后进入我的分配资源,选择3个真实资源,然后用通用替换,但项目只允许你一次替换一个资源 分配第一个资源后,
将不允许您将相同的通用资源分配给其他资源。 有没有一种最佳方法可以做到这一点,而无需维护两个单独的计划(内部和外部)?

Hi all, I've created a resource loaded project plan.  My management would like to send the plan to the client but do not want to show the actual resources, instead just a generic listing.  Is there an easy way to do this?  I thought I could assign, say 300% utilization to the generic name and then go into my assign resource, select the 3 real resources and then replace with the generic, but project only allows you to replace one resource at a time.  Once the first resource is assigned, it won't allow you to assign that same generic resource to other resources.  Is there an optimal way of doing this without having to maintain two separate plans (internal and external)?

推荐答案

试试这个:

1。在项目专业人员中打开计划

1. Open the Plan in project professional

2。在2007年,我认为路径是工具>>从企业建立团队

2. In 2007, I think the path was Tools >> Build Team from Enterprise

3。选择左侧的通用资源和右侧的命名资源。

3. Select the Generic Resource on left and Named Resource On right.

4。选择替换并确定。

4. Select Replace and OK.

这将使用您选择的通用资源替换该命名资源的所有出现次数。

This will replace ALL the occurrences of that named resource with the generic resource you have chosen.


这篇关于用通用资源替换实际资源的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!

查看全文