如何将一个人或团队分配给多个任务,并避免在Project Professional 2010中过度分配 [英] How do I assign one person or team to many tasks and avoid over allocations in Project Professional 2010

查看:1125
本文介绍了如何将一个人或团队分配给多个任务,并避免在Project Professional 2010中过度分配的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

我有一个独特的项目计划。业务不关心跟踪成本或小时数。我有10个"部门"。这将被分配给许多重叠的任务。业务并不真正关心如何或谁在做这项工作,他们只需要b $ b b就可以将它分配给部门经理。显然,当我尝试将一个人安排到8个不同的任务时,Project会在任何地方投掷红旗并导致报告问题。 

I have a unique project plan. The Business is not concerned with tracking cost or Hours. I have 10 "departments" that will be assigned to many tasks that over lap. The business is not really concerned with how or who is doing the work, they just want it assigned to the manager of the department. Obviously when i attempt to schedule one person to 8 different tasks, Project is throwing red flags everywhere and causes issues with reporting. 

有没有办法更改默认工作时间?例如。 John被分配到T1,T2,T3和T4,所有这些都从2013年8月22日开始。有没有办法让我将每个小时的工作时间改为每天工作2小时? 

is there a way to change the default work time? For example. John is assigned to T1,T2,T3 and T4 that all start on 8/22/13. Is there a way that I change his hours to only work for 2 hours each day on each task? 

我不确定实现这一目标的最佳方法是什么。我还考虑过创建部门组并将组分配给任务,但是如何将组分配给多个任务?

I am not sure what the best way is to accomplish this goal. I also thought of creating department groups and assigning the group to the task, but then how do I assign the group to multiple tasks?

推荐答案

jessica00,

jessica00,

是的,您可以为每个资源创建自定义日历,但在您的方案中,我认为没有必要。我只需创建由部门名称标识的10个资源。然后在资源工作表的"最大单位"字段中,将百分比等于
等于每个部门中的个人数。例如,假设销售部门有5个销售人员。将最大单位设置为500%。为每个部门做同样的事情。现在,当您将特定部门分配给多个重叠任务时,如果重叠任务的组合工作超出所分配部门的容量,则只需
获得分配警告。

Yes you could create custom calendars for each resource but in your scenario I don't think that is necessary. I would simply create 10 resources identified by the department name. Then in the Max Units field on the Resource Sheet, set the percentage to equate to the number of individuals in each department. For example, let's say the sales department has 5 salesmen. Set the Max Units to 500%. Do the same for each department. Now when you assign a particular department to a multiple overlapping tasks, you will only get an overallocation warning if the combined work for the overlapping tasks exceeds the capacity of the department assigned.

另外,您可以指定一个额外的任务文本字段(例如Text1)并输入该任务的管理员名称。

In addiition, you could designate an extra task text field (e.g. Text1) and enter the name of the manager for that task.

还有其他方法可以做到这一点,但这是一个简单的方法。

There are other ways to do this, but this is one simple approach.

希望这会有所帮助。

John


这篇关于如何将一个人或团队分配给多个任务,并避免在Project Professional 2010中过度分配的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!