如何让MS Project 2010自动计算百分比资源分配 [英] How to get MS Project 2010 to auto calculate percentage resource allocation

查看:1269
本文介绍了如何让MS Project 2010自动计算百分比资源分配的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

我正在使用MS Project 2010.我有多个任务,每个任务都有一个3人的专门团队,每个任务分配不同的工作量。 MS Project没有反映资源是< 100%已分配,因此自动计划任务将在未来推出


任务是自动计划和固定工作。我将每个资源的工作量分配给任务(见下文),然后手动将持续时间设置为15天。工作分配应该是<每个任务所有资源100%,但显示为100%。


例如


对于任务A. ..


人1 - 超过15天的40小时工作时间b


人2 - 2小时超过15小时天持续时间


人员3 - 5小时工作超过15天


重复以上3个并发任务


 我如何使项目反映出支持资源的工作量不到100%,并且不再将任务推向未来。鉴于我有70个重复任务,我不想手动设置%分配。这是
太高的维护任务。我应该能够在计划的持续时间内设置计划的工作量,然后让Project计算剩下的时间。

解决方案

参考峰值单位而不是单位字段。 该字段计算在2010年进行了修改,现在显示您正在描述的行为。


这是来自Rod Gill的宏,它将根据旧公式计算分配:


http://www.project-systems.co.nz/VBA -sample-代码/ VBASampleResetAssignmentUnits.html


I am using MS Project 2010. I have multiple tasks, each with a dedicated team of 3, who have variable amounts of effort allocated per task. MS Project is not reflecting that resources are < 100% allocated and therefore auto scheduled tasks are pushing out into the future.

Tasks are Auto Scheduled and Fixed Work. I allocate the work effort per resource, to the task (see below), then manually set the duration to 15 days. Work allocation should be < 100% for all resources per task but it is showing as 100%.

eg

For task A...

Person 1 - 40 hours effort over 15 days duration

Person 2 - 2 hrs effort over 15 days duration

Person 3 - 5 hours effort over 15 days duration

Repeat above for 3 concurrent tasks

 How do I make Project reflect the fact that the supporting resources are working at less than 100% effort and to stop pushing the tasks into the future. Given that I have 70 repetitive tasks, I do not want to manually set the % allocation. That is too high a maintenance task. I should be able to just set planned Effort over planned Duration and let Project calculate the rest.

解决方案

Refer to the Peak Units and not the Units field.  That field calculation was modified in 2010, and now displays the behavior you're describing.

Here's a macro from Rod Gill that will calculate Assignments per the old formula:

http://www.project-systems.co.nz/VBA-Sample-Code/VBASampleResetAssignmentUnits.html