问题描述

当我将完成百分比小于100%时,它会在甘特图中显示为线条。当我把它作为100%时它消失了。任何人都可以告诉我它是否是一个错误或解决方案吗?

When I put a percentage complete of less than 100% it is shown in the gantt chart as line. When I put it as 100% it disappears. Can anyone tell me if it is a bug or solution to that?

推荐答案

我能够在甘特图表栏样式中为"进度条"重现上述情况设置为"正在进行中"在"显示...任务"列中。

I am able to reproduce above scenario when in the Gantt Chart Bar Styles for "Progress Bar" has set to "In Progress" in the column "Show for..Task".

您需要更改"显示...任务 "值 到"正常"从"进行中" 然后当您将任务更新为100%时,甘特图进度线不会消失。

You need to change the "Show for.. Task" value to "Normal" from "In Progress" then Gantt Chart Progress line will not disappear when you update the task to 100%.

您可能想参考以下链接可了解有关条形图部分格式的更多详细信息。

You may want to refer the below link to find out more details on format the Bar chart portion.

http://office.microsoft.com/en-us/project-help/format-the-bar-chart-portion- of-a-gantt-view-HA001225368.aspx

希望这会有所帮助。

 

 