单次进入模式和完成百分比 [英] Single entry mode and percentage completed
问题描述
我们想使用单一输入模式功能,但是我们看到以下行为:当用户提交他们的时间表时,实际的小时数确实通过了进入项目计划,但%Complete字段也受到影响。我们需要PM能够
来控制任务的实际进度,这怎么可能呢?最终用户应该只在项目中报告他们的工作时间,而不是搞乱实际的任务进度。
we would like to use the single entry mode feature, however we see the following behaviour: when the user submits their timesheet, the actual hours are indeed passed into the project plan, but the % Complete field is also affected. We need the PM to be able to control the actual progress of the task, how could this be done? The end users should only report their hours in the project, not mess up with the actual task progress.
推荐答案
Hello Spyrosnb
Hello Spyrosnb
%完成按设计工作。 使用"物理完成百分比"如果您想指定另一个完成度量或创建自己的EPM字段。
% Complete is working as designed. Use "Physical % complete" if you want to specify another measure of complete or create your own EPM field.
干杯!