存档的计划仍显示在任务更新列表中 [英] Archived plans still display in task update list

查看:70
本文介绍了存档的计划仍显示在任务更新列表中的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

您好,

我们最近已从MSP 2007和EPM 2007迁移到MSP 2010和EPM 2010.在资源的任务列表中,仍有旧的项目计划已完成显示的内容,即使资源已完成所有工作且MSP 2010中的计划
已保存为已完成,所有剩余工作均为零。为什么即使项目已标记为已完成,旧计划仍会出现在任务列表中并使显示混乱?

We have recently migrated from MSP 2007 and EPM 2007 to MSP 2010 and EPM 2010. In the task list of a resource, there are still old project plans which have been completed that are displaying, even though the resources have completed all work and the plan in MSP 2010 has been saved as completed with all remaining work zero'd. Why are the old plans still appearing in the task list and cluttering the display even though the project has been marked as completed?

谢谢,

Jaco

推荐答案

你还应该使用"关闭任务来更新"。对于那个项目。此功能将从任务列表中消失任务,任务也将被锁定以进行编辑。

您可以在此帖子中找到更多信息。
http://social.technet。 microsoft.com/Forums/en-US/projectserver2010general/thread/47809e4c-5ea1-4b4f-a19d-5f90fd3db350

另一种方式是完成项目,从puslished DB中删除并离开仅在存档的数据库中。

Another way is completed project, delete from puslished DB and leave only in archived DB.

tomas


这篇关于存档的计划仍显示在任务更新列表中的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!

查看全文
登录 关闭
扫码关注1秒登录
发送“验证码”获取 | 15天全站免登陆