在Project Server中配置Bucket任务的最佳方法是什么 [英] What is the best way to configure Bucket tasks in Project Server

查看:89
本文介绍了在Project Server中配置Bucket任务的最佳方法是什么的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

在我们的组织中,我们的团队跨越了许多开发项目,并为这些团队提供支持。

In our organiziation we have teams that span many development projects and do support of those teams.

我们正在努力追踪这些支持团队为不同的团队付出的努力一般项目中的开发项目发布到我们的项目服务器PWA 20101,并分配了企业资源。

We are trying to track the effort that these support groups put towards the different development projects in a general project Which is published to our project server PWA 20101, and has enterprise resources assigned to it.

我需要了解的是配置任务的最佳方法是什么跨越大量的时间(可能是一年),资源可能每天或每周花费一两个小时。

What I need to understand is what is the best way to configure tasks that span a wide amount of time (possibly a year) where resources might put an hour or two towards each day or week.

我们希望这些任务显示在时间表区域,并且资源很容易进入时间。我无法正确配置。如果我针对任务设置了%或时间或精力,则PWA会自动填写任务。
我创建了一个约束为"尽快开始"的任务。并且已经进入截止日期为12月31日。但通常并非所有任务都显示在时间表中,或者任务视图或项目专业人员将更改结束日期或开始日期等...我将这些任务称为
任务桶任务,其中没有具体数量努力或特定的努力可以轻松约束。

We would like these tasks to show up in the timesheet area, and be easy for resources to enter time against. I am having trouble configuring this properly. If I set a % or time or effort against the task then PWA fills in the task with time automatically. I create the task with constraint of "start as soon as possible" and have been entering an end date of December 31st. But often not all the tasks show up in the timesheet or the taskview or Project pro will change the end date or start date, etc... I call these kinds of tasks bucket tasks, where there is not a specific amount of effort or a specific effort that can be constrained easily.

我脑海中的任务有点像管理项目或PWA中的任务。我不确定我是否在这里有意义但是如果有配方或最佳实践方法来配置它?我们确实在PS2003中有这样的东西,我们没有结束日期,
但如果我这样做,任务就不会出现在时间表视图中。

The tasks in my mind would sort of be like the tasks in the Admin project or PWA. I am not sure if I am making sense here but if there a formula or a best practices way to configure this? We did have something like this in PS2003, and we had no end date, but if I do that the tasks do no appear in the timesheet view.

我有一些这样的项目可以真正使用帮助吗?

I have a few projects like this and could really use the help?

Jane Wilson Steeves团队负责人 - 工程工具合并医疗保健

Jane Wilson Steeves Team Lead - Engineering Tools Merge Healthcare

推荐答案

嘿简,

我希望我理解你想要实现的目标,所以我不会给你错误的建议。

I hope i understood what you are trying to achieve so i wont give you the wrong advice.

我不太明白你是否希望任务在31/12结束,但如果你这样做,你可以添加一个"Bucket"。任务与X工作并安排所有相关的资源,如10%,20%所以他们的小时将在一年中蔓延(但没有必要,他们将
根据需要更新他们的小时)但我建议你这样做资源不会被分配到每天很多小时。

I don't quite understand if you want the task to end at 31/12 but if you do you can add a "Bucket" task with X work and schedule all relevant resource to something like 10% , 20% so their hours will spread upon the year (but it's not necessary, they will update their hours as needed) but i suggest you do that so the resource won't be assigned to much hours per day.

基本上任务保持在2012年1月1日至12月31日期间 你需要执行以下步骤:

Basically for the task to remain on the dates of 1/1/12 - 31/12/12  You need to do the following steps:

1。将任务分配为固定持续时间,并且努力驱动(也分配资源)

1. assign the task as a Fixed duration with effort driven (assign the resources as well)

2。将任务的开始日期作为年度的开始日期(1/1/12)

2. give the task the start date as the beginning of the year (1/1/12)

3。在持续时间字段中插入52.2周(这会将完成日期更改为一年中的最后一个工作日)

3. in the duration field insert 52.2 wks (this will change the finish date to the last working day of the year)

4。在这一点上,如果资源将在年中增加小时数任务的日期将移动,我想这是你的问题。  为了防止它更新0.01小时(或其他没有效果的小值)到实际工作字段,它将强制
任务从1/1/12开始,因为这是一个固定的持续时间任务,无论是资源将更新它将保持相同的开始和结束日期。

4. at this point if the resources will add hours in the middle of the year the task's dates will move and i guess this is your problem.  to prevent it update 0.01 hrs (or another small value that have no effect) to the actual work field it will force the task to start at 1/1/12 and because this is a fixed duration task no matter what the resource will update it will remain with the same start and finish dates.

希望这会有所帮助......

Hope this helps...

 


这篇关于在Project Server中配置Bucket任务的最佳方法是什么的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!

查看全文