在计划中断期间限制访问Project Server 2010的最佳做法是什么 [英] What is the best practise to Restrict Access to Project Server 2010 during planned outage

查看:52
本文介绍了在计划中断期间限制访问Project Server 2010的最佳做法是什么的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

您好,

我们有Project Server 2010环境,并想知道在计划中断期间限制访问Project Server 2010的最佳方法是什么?

We have Project Server 2010 environment, and wondering what is the best way to Restrict Access to Project Server 2010 during planned outage?

问候,

Kishore Dodda

Kishore Dodda

Kishore Dodda

Kishore Dodda

推荐答案

Kishore,

Kishore,

1. 告知所有PWA和Project Pro用户有关中断窗口的信息。

1. Inform all your PWA and Project Pro user about the outage windows.

2。接下来确保没有项目,资源和其他企业实体签出。如果有,则签入。

2. Next make sure that there are no projects, resources and other enterprise entities checked-out. If there are then have them checked in.

3。根据中断窗口,确保所有预定作业  (管理备份,OLAP多维数据集生成,ERP \ Group AD同步等)不会在相同的时间范围内启动。如果有冲突,请采取适当的措施

3. Depending on outage window, make sure that all your scheduled jobs  (Administrative backup, OLAP cube build, ERP\Group AD sync etc) are not starting during same timeframe. If conflicting then take appropriate action

4。确保 中没有待处理的职位Project Server队列。

4. Make sure that there are no pending jobs in  Project Server queue.

5。从IIS停止PWA站点并禁用Project Application Service。

5. Stop PWA site from IIS and disable Project Application Service.

在停机完成后以相反的方式重复相同的过程。

Repeat same process in reverse manner after outage is completed.

希望这有帮助。


这篇关于在计划中断期间限制访问Project Server 2010的最佳做法是什么的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!