计划中未填充的实际完成日期 - Project Server 2010 [英] Actual Finish Date Not Populating in Schedule - Project Server 2010
问题描述
我有一个场景,资源在%Work Complete& ;;上完成了100%的任务更新。将完成日期从9/14更改为9/11。 "实际完成日期"似乎在任务更新中填充。屏幕截图如下?
为什么日程表中没有填写"实际完成日期"字段?谢谢......
嗨StacyLo,
该作业的工作已完成,这就是为什么您在"任务"页面上看到100%完成但该任务的完成百分比(持续时间)不是100%,这就是为什么您没有看到填充实际完成日期的原因。如果任务完成100%,则设置完成该任务的
%将设置实际完成日期。
谢谢
保罗
I have a scenerio where a resource entered a task update of 100% on % Work Complete & changed the finish date from 9/14 to 9/11. The 'Actual Finish Date' appears to be populated on the task update. Screen shots below?
Why is this 'Actual Finish Date' field not populated in the schedule? Thanks ...
Hi StacyLo,
The work is complete for that assignment, that is why you see 100% complete on the Tasks page but the %complete (duration) for the task is not 100% that is why you are not seeing Actual Finish date populated. If the task is 100% complete setting the % complete for that task will give set the actual finish date.
Thanks
Paul