问题描述

环境是Project Server 2010 + SP1 + 6月CU刷新


问题 - 资源在计划开始和计划之间输入的实际完成日期。对于固定持续时间任务,计划完成不会将任务标记为100%完成%。


我们在PWA中创建了一个名为Actual Finish的视图。资源转到PWA>任务>实际完成视图,只需输入完成任务的日期。资源无法通过PWA访问Project Professional中的项目。只有
项目经理可以访问Project Professional。


现在问题是资源是否在中途完成任务(比如 2011年12月15日 )并且
计划开始时间是2011年12月10日计划结束时间是2011年12月20日
任务永远不会标记为100%完成。它被标记为100%%WorkComplete,但这并未将任务标记为完成。


这被Microsoft识别为bug,请参阅thread

解决方案

嗨尼罗什,


我模拟了您的场景(100%可重现) 我注意到即使在MSP中,实际完成日期也没有填入通过PWA输入的值...所以它很难将这些任务作为异常过滤掉。


尽管如此,通过MSP将剩余持续时间更改为零,您的"%(持续时间)已完成"。将成为100% 并且实际完成日期也是正确的!


这可以暂时完成这项工作吗?


问候

Wim


 


Environment is Project Server 2010 + SP1 + June CU Refresh

Issue - An Actual Finish Date entered by resource between Planned Start & Planned Finish does not mark Task as 100% for %Complete for Fixed Duration Tasks.

We have created a view in PWA called as Actual Finish. Resources goto PWA > Tasks > Actual Finish View, and simply enter the date on which they completed the task. Resources dont have access to the project in Project Professional, only via PWA. Only the Project Managers have access to Project Professional.

Now the problem is if the resources complete the task midway (say on Dec 15, 2011) and the planned start is Dec 10, 2011, planned finish is Dec 20, 2011, the task is never marked as 100% %Complete. It is marked 100% %WorkComplete, but that does not mark the task as complete.

This was identified by Microsoft as a bug, see thread http://social.technet.microsoft.com/Forums/en-US/projectserver2010general/thread/129cee71-4675-4026-b107-6789210cf37d (back in April 2011)

Is this still the case?

Has anyone found a solution (other than manually marking the task as 100% %Complete in PRO)?


Nilesh Kelkar | nkelkar.wordpress.com

解决方案

Hi Nilesh,

I simulated your scenario (100% reproduceable) and I noticed that even in MSP, the Actual Finish date is not filled in with the value entered via PWA...So it becomes difficult to filter those task out as anomalies.

Nevertheless, by changing the remaining duration to zero via MSP, your "% (Duration) complete" will become 100% and the actual finish date will be correct too!

Can this do the job for now?

Regards
Wim

 