问题描述

我遇到问题,如果在创建时间表后添加或更改了任务,则Timesheets不会使用计划工作进行更新。有没有办法在这种情况下更新时间表中的计划工作?

I have a problem, that Timesheets are not updated with the Planned work, if the task is added or changed after the Timesheet is created. Is there a way to update planned work in Timesheet in this situation?

重现的步骤:

1。创建具有task1的项目,工作量为1天。

1. Project with task1 is created with work amount 1 day.

2。创建该期间的时间表。

2. Create timesheet for that period.

3。项目更新,任务1工作量为2天。并且添加了工作量为3天的task2。

3. Project is updated that task1 work amount is 2 days. And task2 with work amount 3 days is added.

=>因此,在任务1的时间表仍然计划工作量是1天。还有task2,但没有计划的工作。

=> As a result in Timesheet for task1 still planned work amount is 1 day. And there is task2, but without planned work.

我发现,我可以通过删除和重新创建时间表来更新计划的工作。还有更好的方法吗?

I have found out, that I can update planned work by deleting and re-creating timesheet. Is there some better way?

推荐答案

Joseley。 这将是一个值得关注的主题。 我假设您使用的是MSProject 2010 Enterprise。 一种解决方案,也许不是优选的,是让用户删除他们的时间表然后重新创建它。 确保他们首先转储到Excel
并让他们检查他们所做的任何条目,特别是在时间表删除中有时会丢失的任何管理类别。

Hi, Joseley.  This will be a thread to watch.  I'll assume you are using MSProject 2010 Enterprise.  One solution, perhaps not perferred, is to have the user delete their timesheet then re-create it.  Make sure they do the dump to Excel first and have them check any entries they made, particularly on any Administrative categories which can sometimes get lost in timesheet deletions.

Alan

QBE北美

608-825-5073

608-825-5073


这篇关于Project Server 2010时间表不显示计划的工作的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!