Project Server 2010视图和时间表问题。 [英] Project Server 2010 views and timesheet issue.

查看:97
本文介绍了Project Server 2010视图和时间表问题。的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

您好,

在Project Server 2010中,我有一个项目级自定义字段(自由文本类型)。如果我尝试在Project Center中创建视图并根据自由文本字段对项目进行分组,则无法看到该视图。错误说'无法与服务器通信'
早先出现但升级到SP1后,错误已停止,但视图只是拒绝加载。如果删除了自由文本字段分组,它就可以正常工作。

In Project Server 2010, I have a project level custom field (free text type). If I try to create a view in Project Center and group the projects according to the free text field, I am unable to see the view. Error saying 'Cannot communicate to the server' was coming earlier but after upgrading to SP1, the error has stopped but the view simply refuses to load. If the free text field grouping is removed, it works absolutely fine.

第二个问题是在单一条目模式下配置的时间表中,某些网格对任务是灰色的。我能够针对某些任务输入实际值(完成百分比和明天实际值),但有些网格完全随机灰显,没有任何可见的
逻辑。

Second issue is that in Timesheet, configured in single entry mode, some grids are greyed out against tasks. I am able to enter actuals (% complete and day wise actuals) against some tasks but some grids are randomly greyed out totally, without any visible logic.

请帮助我问题。

提前致谢

Atul Sharma,MCTS

Atul Sharma, MCTS

推荐答案

您的时间表问题:当单元格不适合项目的跟踪方法时,它们会变灰。如果网格是"随机的"。灰色,我假设不同的跟踪方法应用于您的项目。如果您无法输入%完成和每天的小时数,
您应该能够在左侧网格中输入实际工时和剩余工时。 (这是三种可用跟踪方法中的第三种。)

for your timesheet issue: cells are greyed out when they don't fit to tracking method of a project. If grids are "randomly" greyed out, I assume that different tracking methods are applied to your projects. If you can't enter %complete and hours per day, you should be able to enter Actual Work and Remaining Work in left grid. (This is the third of three available tracking methods.)

您可以在右侧窗格中更改Project Professional中的跟踪方法:文件 - 信息。

You can change tracking method within Project Professional: File - Info in the very right pane.

您的项目服务器管理员可以更改Project Web App中的默认跟踪方法 - 服务器设置 - 任务设置和显示:每个时段完成的工时(您的管理员还可以强制PM使用一种方法)。

Your project Server administrator can change default tracking method in Project Web App - Server Settings - Tasks Settings and Display: Hours of Work done per period (your admin can also force PMs to use one method).

关心

Barbara

Regards
Barbara

 