Project Server 2010导入问题 [英] Project Server 2010 import problem

查看:64
本文介绍了Project Server 2010导入问题的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

我有几个项目在Project Server 2010上导出为xml,我需要导入它们。


我们正在使用带有2012年6月累积更新的Project Server 2010 SP1。微软告诉我,我需要将所有项目导出为xml并将它们导入到另一个站点。 BTW-I还尝试从Save for Sharing导出为mpp。


当我导入项目时,它会询问我要用企业资源替换的本地资源。我对所有人说是,然后当我转到资源表时,我看到2个相同的名称,一个本地资源和另一个企业资源。两者都有实际的
与不同的任务一起工作。 


我试图根据Gary Chefetz的书替换本地资源的任务分配,但这对我没有帮助。


如何用所有任务和实际的企业资源替换所有本地资源?



谢谢,


Haim Beyhan


Haim Beyhan

解决方案

< blockquote>请参阅以下文章:
$
http://office.microsoft.com/en-us/project-help/add-resources-to-your-project-HA010377762.aspx





    • 要使用企业资源替换现有资源,请在项目资源列中,选择要替换的资源或常规资源。 ; 企业资源,选择新的企业
      资源,然后点击替换


更换资源时,如果已完成任何实际工作,则不会删除替换资源。替换资源将分配剩余工作。


 将正在进行的任务的实际工作从本地资源移动到企业资源

http://www.epmpartners.com.au/blog/replacing-local-resources-with-enterprise-resources-for-in-progress-tasks/

I have couple of projects exported on Project Server 2010 as xml and I need to import them.

We're using Project Server 2010 SP1 with June 2012 cumulative updates. Microsoft told me that I need to export all the projects as xml and import them to another site. BTW-I tried also to export as mpp from Save for Sharing.

When I import the projects, it's asking me about the local resources to be replaced by enterprise resources. I say Yes to All and then when I go to Resource Sheet, I see 2 same names, one local resource and the other enterprise resource. Both have actual work with different tasks. 

I tried to replace the assignments of the tasks from local resources according to Gary Chefetz book but it didn't help me.

How can I replace all local resources with enterprise resources for all tasks and actuals?

Thanks,

Haim Beyhan


Haim Beyhan

解决方案

Please see the below article:
http://office.microsoft.com/en-us/project-help/add-resources-to-your-project-HA010377762.aspx

    • To replace an existing resource with an enterprise resource, in the Project Resource column, select the resource or generic resource that you want to replace. Under Enterprise Resource, select the new enterprise resource, and then click Replace.

When you replace a resource, the replaced resource is not removed if they have completed any actual work. The replacement resource is assigned the remaining work.

 to move the actual work for in progress tasks from a local resource to an enterprise resource
http://www.epmpartners.com.au/blog/replacing-local-resources-with-enterprise-resources-for-in-progress-tasks/


这篇关于Project Server 2010导入问题的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!

查看全文
登录 关闭
扫码关注1秒登录
发送“验证码”获取 | 15天全站免登陆