Portfolio Server 2007升级到Project Server 2010 [英] Portfolio Server 2007 Upgrade to Project Server 2010

查看:93
本文介绍了Portfolio Server 2007升级到Project Server 2010的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

我们正在使用Portfolio Server 2007和Project Server 2007,并希望升级到Project Server 2010. 

We are using Portfolio Server 2007 and Project Server 2007 and would like to upgrade to Project Server 2010. 

在"预算跟踪/标签"中,我们使用的核心功能是向下钻取至第3级以获取财务信息。 基本上我们有


建立了一个财务/预算树并使用第三级来附加实际的$$$。

我被告知项目中不存在此功能Server 2010,或者它的处理方式可能不同。

有人可以解释或添加这个特定的功能吗?

Within 'Budget Tracking/Tab', the core functionality we use is the drill down to 3rd level for financial information.  Basically we have
established a finance/budget tree and use 3rd level to attach actual $$$.
I was told this functionality does not exist in Project Server 2010, or perhaps its just handled differently.
Can someone explain or add to this specific piece of functionality?

bex

推荐答案

我的一位同事建议:

one of my collegues suggests:

我敢肯定我们的一位聪明的同事可以建议如何分层成本可以在PS2010中管理。在最简单的级别,您可以在项目计划中使用任务来模拟成本类型,然后简单地将值输入到"总成本"中。任务领域。
然后,这将执行类似于PPS如何执行的汇总功能。您甚至可以在Project Center中构建过滤视图以仅显示成本字段。哎呀 - 你可以写一份报告来拉动那些"成本任务"。来自投资组合中的所有项目。

I'm sure one of our more clever coworkers can suggest how tiered cost can be managed in PS2010. At the simplest level you could mimic this in a project plan using tasks to emulate the cost types, then simply input the value to a "total cost" task field. This would then perform the roll-up functionality similar to how PPS did it. You could even build filtered views in Project Center to show just the cost fields. Heck - you could write a report to just pull those "cost tasks" from all projects in a portfolio.

当然,这是一种简单的方法,我相信有更聪明的方法可以做到这一点。项目使用工作,物料和成本资源类型来跟踪不同类型的成本,来自PPS的人可以使用此功能模拟成本跟踪
,因为他们在PPS中执行此操作。 (即创建名为"操作软件"的材料资源,或使用工作常规资源来计划资源成本估算。)​​

Of course, that's a simple approach, and I'm sure there's a more clever way to do it. Project uses Work, Material and Cost resource types to track different kinds of cost, and someone coming from PPS could use this functionality to emulate cost tracking as they did it in PPS. (I.e. create a Material resource called "Operating Software", or use Work Generic Resources to plan resource cost estimates.)

来自PPS的人员需要知道Project Server是"自下而上面向对象,而Portfolio Server绝对是"自上而下"。这是思维方式和功能上的差异。

People coming from PPS will need to learn that Project Server is "bottom up" oriented, whereas Portfolio Server was most definitely "top down". It's a difference in mindset as well as functionality.

Ken Prush

Ken Prush

www.pcubed.com


这篇关于Portfolio Server 2007升级到Project Server 2010的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!