无法编辑PWA的计划 [英] Not able to edit the schedule on PWA

查看:64
本文介绍了无法编辑PWA的计划的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

我已经在EPT中附加了一个模板,并且成功地在PWA中使用该EPT创建了计划,但我无法编辑计划,除非我回到项目中心并检查该项目,这给用户带来了很多麻烦。

I have attached a template in EPT and schedule got created with that EPT in PWA succesfully, but I am not able to edit the schedule until and unless I go back to project center and check in that project, this is creating a lot of trouble for the user.

我验证了默认选项  "基本项目计划"在初始配置中,我能够做到这一点。

I verifield the default option  "Basic Project Plan" that comes in initial configuration, where I am able to do this.

任何想法可能是什么原因。

Any idea what could be the reason.

 

推荐答案

Vinay:

Vinay:

这是否发生在所有模板上你创建或只是这个特定的?你在跑什么SP?该计划是否包含固定工作或努力驱动的任务?

Does this happen to all templates that you create or just this specific one? What SP are you running? Does the plan contain fixed work or effort-driven tasks?


这篇关于无法编辑PWA的计划的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!

查看全文
登录 关闭
扫码关注1秒登录