我该如何计算“进度”?基于今天的日期,开始日期和预测结束日期的项目(%格式) [英] how can i calculate "progress" of a project based on today's date, the start date and the forecasted end date (% format)
问题描述
大家
我希望基本上以%条款显示.....项目进度基于我的2现有日期列
即"开始日期"是1月1日,"预测结束日期"是11月1日。
大约10个月。说今天是8月1日 - 然后是"进展"。应该是大约70%.....
使用具有以下公式的计算列:
= DATEDIF([今天],[开始日期],"d")/ DATEDIF([结束日期],[开始日期],"d")请在此处查看示例:
https://www.interfacett.com/blogs/how-to-create-calculated-column-showing-difference-between-dates/
公式:
https://docs.microsoft.com/en-us/previous-versions/office/developer/sharepoint-2010/bb862071(v %3Doffice.14)
希望这会帮助!
块引用>
hi all
i want to basically show in % terms.....the project progress based on my 2 existing date columns
i.e. "start date" was 1st jan, "forecasted end date" is 1st november.
thats approx 10 months. say today is 1st august - then the "progress" should be approx 70%.....
解决方案Use calculated column with the following formula:
=DATEDIF([Today] , [start date] ,"d")/DATEDIF([forcasted end date] , [start date] ,"d")Please check an example here:
https://www.interfacett.com/blogs/how-to-create-calculated-column-showing-difference-between-dates/
Formulas:
https://docs.microsoft.com/en-us/previous-versions/office/developer/sharepoint-2010/bb862071(v%3Doffice.14)
Hope this will help!