Azure董事会-如何在sprint中查找已预订的团队成员 [英] Azure Boards - How to find over booked team member in sprint

查看:70
本文介绍了Azure董事会-如何在sprint中查找已预订的团队成员的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

我们最近开始使用Azure板和Sprint.假设我们有两个团队成员,每个成员每周工作20个小时,每周冲刺2次.团队的总冲刺能力为80小时.现在让我说我有80个小时的任务,有60个小时分配给团队成员A,有20个小时分配给团队成员B.

该冲刺似乎是基于团队的,正在寻找一些审核工具来适当地平衡工作负载.TIA.

解决方案

当您过滤以显示工作详细信息"时,将在sprint页面上捕获您要查找的内容.您可以参考

We've recently started using Azure Boards and Sprints. Say we have two Team members, each with 20 hours a week capacity, 2 week sprint. Total team sprint capacity is then 80 hours. Now lets say I have 80 hours of tasks, 60 are assigned to team member A, 20 to team member B. Accident of course, but where in Azure Boards can we discover this aside from adding up each task effort remaining?

The sprint seems very team based, looking for some audit tools to balance the workload properly. TIA.

解决方案

What you are looking for is captured on the sprint page when you filter to show Work Details. You can reference the documentation to see it in action. This is driven off the "Remaining Work" field, so you will have to populate and keep it updated during the sprint to see it updating daily in real-time.

这篇关于Azure董事会-如何在sprint中查找已预订的团队成员的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!

查看全文
登录 关闭
扫码关注1秒登录
发送“验证码”获取 | 15天全站免登陆