救命!! MS Project Prof设置“开始不早于”更新计划时的约束 [英] Help!! MS Project Prof setting "Start no earlier than" constraints when I update schedule

查看:607
本文介绍了救命!! MS Project Prof设置“开始不早于”更新计划时的约束的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

您好

我的日程安排符合施工需求日期。  我已正常输入所有摘要任务及其子任务,输入工时并应用相关资源获取持续时间。  我按资源链接,也按任务依赖关系
链接。  我已从今天的日期更新了预定日期,但它似乎设置了"不早于"的开始时间。限制我的800行计划中的每个任务。  值得一提的是,起始约束似乎是
违约到我设定的最后状态日期(1月30日),但在其他情况下则是1月26日。

I have a schedule that is set up in line with construction need dates.  I've entered all the summary tasks and their sub tasks as normal, entered work hours and applied the relevant resource to obtain duration.  I've linked by resource and also by task dependencies.  I've updated the scheduled from today's date but it seems to set a "start no earlier than " constraint against every task in my 800 line schedule.  It might be worth mentioning that the start constraint seems to be defaulting to the last status date I had set (30th Jan) in some cases but in others it's the 26th Jan.

这都是在练级之前。  当我升级时,它似乎工作正常并且正在做我期望它做的事情(我已将参数更改为优先级,标准)。

This is all prior to levelling.  When I level, it seems to work fine and is doing what I expect it to do (I've changed parameters to Priority, Standard).

有人可以解释这些开始没有先前的限制吗?  只有在我重新安排时才会发生。

Can someone please explain what these start no earlier constraints are?  It's only happening as soon as I reschedule.

谢谢

Jo

J Day

推荐答案

你对你所做的事情的描述有点粗糙,但是这里有。

Your description of what you did is a bit rough, but here goes.

如果一个任务计划在过去相对于状态日期开始,但它实际上没有开始,因为过去无法计划启动某些事情,当您更新计划时,MSP会将这些任务移动到尽快启动未来相对
到状态日期,它通过设置SNET日期约束来实现。

If a task is scheduled to start in the past relative to the status date, but it has not actually started, then because it is not possible to plan to start something in the past, when you update the plan MSP moves those tasks to start asap in the future relative to the status date, and it does this by setting a SNET date constraint.

你期望什么?

如果计划在过去开始的任务确实在过去开始,那么您需要输入实际开始日期和实际持续时间。如果任务在计划开始时实际开始,并且该任务从那时起持续进行
,直到tstaus日期,那么你只需点击轨道上的标记即可输入实际的开始日期和你的实际持续时间。

If the task which was scheduled to start in the past did actually start in the past, then you need to input the actual start date and actual duration. If the task actually started when it was scheduled to start, and if the task has been continuously in progress since then and up to the tstaus date, then you can just click mark on track and it will input the actual start date and actual duration for you.


这篇关于救命!! MS Project Prof设置“开始不早于”更新计划时的约束的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!