问题描述

亲爱的,

我很想知道如何从我的MSP 2016计划中提取每周的小时数。我确定了每周活动的持续时间,现在我想要提取每周我放入的小时数。所以我想从我的MSP计划
中扣除每周的小时数。

I would love to know how to extract the hours per week from my MSP 2016 planning. I determined the durations of the activities per week, now I want to extract how many hours per week I have put in. So I want to pull out the hours per week from my MSP planning.

任何人都可以教我怎么做;这将是非常好的。

Can anyone teach me how to do; would be more than great.

问候,

Ingenieur X

Ingenieur X

推荐答案

IngenieurX,

IngenieurX,

您每周必须投入的小时数"直接取决于您的作业级别。如果您全职工作,则每个任务的工作时间与每个任务的持续时间相同。如果你只工作一半时间,那么工作时间
将是持续时间的一半。

The number of hours you "have to put in per week" is directly dependent on your assignment level. If you work full time, then the work hours per task is the same as the duration hours per task. If you are only working half time then the work hours will be half the duration hours.

你说你想要"拉出每周的工作时间"。这到底是什么意思呢?这是否意味着您只想查看它,还是意味着您要将该数据导出到其他应用程序?如果您只是想查看它,通过查看任务使用情况或资源使用情况视图,可以获得信息

You say you want to "pull out the hours per week". What exactly does that mean? Does it mean you simply want to view it or does it mean you want to export that data to some other application? If you just want to view it, the information is readily available by looking at either the Task Usage or Resource Usage views.

因此,为了进一步提供帮助,我们需要了解更多信息。

So, in order to help further, we need to know more information.

John