将计划从msp 2007迁移到msp 2010时重复资源 [英] Duplicate Resources when migrating plans from msp 2007 to msp 2010

查看:98
本文介绍了将计划从msp 2007迁移到msp 2010时重复资源的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

Hello All,


将计划从msp 2007迁移到msp 2010.我在资源视图中有重复的

资源。资源是使用本地域创建的。在msp 2007中,在msp2010中,资源是使用不同的资源创建的。


您能帮忙解决这个问题吗?


谢谢和亲切的问候


Soudha

解决方案


您可以打开项目计划,将本地资源重命名为与企业资源名称完全相同的名称,保存计划并确认本地资源将转换为企业资源。 / p>

希望这会有所帮助,


Renke


​Hello All,

While migrating plans from msp 2007 to msp 2010. I am having duplicate
resources in resource view. The resources were created using local domain  in msp 2007 while in msp2010 , the resources were created using a different one

Can you please help to solve this?

Thanks and Kind Regards

Soudha

解决方案

Hi,

you can open the project plan, rename the local resource to a name that is exactly the same as the one of the Enterprise Resource, save the plan and confirm that the local resource will be converted to Enterprise Resources.

Hope this helps,

Renke


这篇关于将计划从msp 2007迁移到msp 2010时重复资源的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!