时间表上的任务,0小时“剩余工作” [英] Tasks on Timesheet with 0 hours "Remaining Work"

查看:80
本文介绍了时间表上的任务,0小时“剩余工作”的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

我是我公司的Microsoft Project Server的备份,但我是该工具的新手。主要支持是休假一周。今天早上我收到了一个事件,许多用户在他们的时间表上显示了20多个任务,但是"剩余的
工作"是0h。我之前被告知,在当前时间表期间未安排的任务和/或剩余工作时间为0小时的任务将不会显示在他们的时间表上。对于为该项目分配了
的30多人,我怎样才能完成0h的任务?我不确定它是否也影响其他人。

I am the backup for Microsoft Project Server at my company, but I'm new to the tool. The primary support is out for a week of vacation. This morning I received an incident where many users had 20+ tasks show up on their time sheets, but "Remaining work" was 0h. I was told previously that tasks that were not scheduled during the current timesheet period and/or have 0 hours of remaining work, would not show up on their time sheet. How can I make the tasks with 0h go away for the 30+ people assigned to the project? I'm not sure if it's also affecting others.

推荐答案

您可以打开资源分配的项目,并将这些任务标记为已完成,它们不会出现在他们的时间表中。
You can open the project in which the resources have assignments and mark those tasks as completed so that they will not appear in their timesheets.


这篇关于时间表上的任务,0小时“剩余工作”的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!

查看全文