我们公司正在切换到Project Server 2010.他们不想使用该软件来跟踪向客户收费的小时数。但是,他们希望跟踪小时数,以便他们可以在几个
的项目中分配资源。 我正在为团队更新计划,但我们正在尝试按预期使用系统,因此我们现在让他们更新他们的任务。这给那些已经过于分散的人带来了行政负担。所以我的问题......&bbsp;
使用任务更新/时间表功能与我输入团队的更新(完成百分比,开始/结束日期等等)有任何好处。

Our company is switching to Project Server 2010. They do not want to use the software for keep track of hours being billed to the customer. They do however, want to keep track of hours so they can allocate resources across a couple of projects.  I was keeping the plan updated for the team, but we are trying to use the system as intended so we now have them updating their tasks. This has put an administrative burden on those that are already spread too thin. So my question...... Is there any benifit to using the Task Update/Timesheet features vs. me entering the updates (% complete, Start/Finish date, etc...) for the team.

推荐答案

绝对!

其中一个关键优势使用项目服务器是为了让项目经理不必追逐要求更新的人,然后更新项目计划。使用Timesheets / Task Updates可以对完成
这些任务的团队成员负责,并提供更准确的信息,同时减少PM的管理负担。

One of the key advantages of using project Server is so that the Project Managers do not have to chase people asking for updates and then update the project plans. Using Timesheets/Task Updates puts the responsibility on the team members who are completing these tasks, and also provides more accurate information, while reducing the Administrative burden on the PMs.

此外,您不必同时使用时间表和任务更新。如果你的目的只是为了捕捉"项目"相关的小时,然后任务更新很好。时间表允许捕获甚至非项目时间,例如假期,管理员等。

Also, You do not have to use BOTH time sheets and Task Updates. If your intention is only to capture "project" related hours, then Task Updates are fine. Timesheets allow capture of  even the non-project time like Vacation, admin etc.,

请参阅此链接,了解时间表在这方面的帮助:  http://www.epmarchitects.com/understanding-how-planned-non-working -time-works-project-server-2010

Please see this link as to how timesheets help in this regard: http://www.epmarchitects.com/understanding-how-planned-non-working-time-works-project-server-2010

最后,您必须在设置时选择跟踪方法。以下是各种跟踪方法的一个很好的解释:

And finally, you will have to choose a method of tracking when you set this up. Here is a good explanation of various tracking methods:

http://khurramjamshed.blogspot.com/2011/02/project-server-project-progress.html

希望这会有所帮助!