问题描述

使用新的Team Foundation Server 11和Sprint规划如何更新当前迭代集以及如何重命名迭代会影响"当前迭代"。查询。

With the new Team Foundation Server 11 and Sprint Planning how is the Current Iteration Set and how does renaming the Iteration affect the "Current Iteration" queries.

推荐答案

迭代具有与之关联的开始数据和结束日期。 

The iterations have a start data and end date associated to them. 

让我们看看例如,如果你在tfs 11中创建了两个迭代,让我们说iteration1和iteration2,你设置iteration1的开始日期为20日至8月3日,迭代2为9月3日至19日,然后在tfs任务板中你应该是能够
将iteration2视为当前迭代。这可以通过查看迭代的开始和结束日期与今天的日期来获取。 

Lets take an example, if you have two iterations created in tfs 11, lets say iteration1 and iteration2 and you set up the start date of iteration1 as 20th feb to 8th march and iteration 2 as 9th march to 19th march then in tfs task board you should be able to see iteration2 as the current iteration. This is simply picked up by looking at the start and end date of the iteration vs the date today. 

重命名迭代不会对AFAIK产生任何影响,但是,如果你是删除迭代时,系统将提示您选择要分配当前分配的工作项的迭代。  关于如何设置
迭代路径和迭代开始的文档&结束日期  http://msdn.microsoft.com/en- us / library / ms181692(v = vs.110).aspx#iterations

Renaming the iteration will not have any impact AFAIK, however, if you were to delete the iteration you will be prompted to select the iteration where you would like the currently assigned work items to be allocated.  Documentation on how to set up iteration path and iteration start & end dates http://msdn.microsoft.com/en-us/library/ms181692(v=vs.110).aspx#iterations

如果您有任何后续查询,请随时回复我们。

Feel free to get back to us if you have any follow up queries.

HTH

干杯,塔伦

HTH
Cheers, Tarun