问题描述

大家好,

我们正在使用项目服务器2013并尝试计算显示图形指示的值。 [完成差异] / [持续时间] * 100。但我总是把价值变为空。

We are using project server 2013 and trying to calculate the value to show the graphical  indicator. [Finish Variance]/[Duration]*100 . But I am always getting value as empty.

提前致谢,Taj

推荐答案

嗨Taj,

首先,您应该确保保存基线以获得有效的方差值。

First you should ensure to have a baseline saved in order to have a valid variance value.

然后我建议先删除图形指标,然后确定计算是否有效。

Then I'd suggest first to remove the graphical indicator and have just he value to check if the calculation works.

最后根据您已验证的值。请记住,在创建自定义字段后需要发布项目。

Finally configure the graphical indicator accordingly based on the values you've verified. Remember that the projects needs to be published after creating the custom field.