Project Server 2010项目状态自定义字段 [英] Project Server 2010 Project Status Custom Fields

查看:97
本文介绍了Project Server 2010项目状态自定义字段的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

大家好,

我们正在尝试使用项目服务器2010.我已经看到一些演示,其中自定义字段包含项目计划,项目成本,项目健康,项目质量,项目资源,项目风险,项目问题。如何计算。
根据我的 低估项目 时间表 可以使用    start,完成日期和%完成。项目成本核算也可以使用成本和实际成本计算。如何计算其余字段。或者
是自动计算的,并且可以在DB中报告。

We are trying with project server 2010. I have seen some demos where the custom field with graphical indicators for Project Schedule,Project Cost, Project Health, Project Quality, Project Resource, Project Risk,Project Issues. How this will be calculated. According to my understating Project schedule can be calculated using  start , finish date and % completed. Also Project Costing can be calculated using cost and actual cost. How rest of the fields will be calculated. Or is it automatically calculated and  available reporting in DB.

提前致谢

推荐答案

您好Arun,



是的,您可以在报告数据库中找到相关信息。项目估算成本将根据Assiged工作*资源率计算。 Actaul成本将基于实际工作和资源利率加上一些其他因素,如材料/成本资源。
项目风险&问题基于项目工作区中创建的问题/风险。




项目服务器& professional有一个复杂的调度引擎,可以完成所有计算。您可以在MS项目中选择自动计算开/关。



几乎所有信息都可以在Projects erver报告数据库中找到。我建议下载Projects erver 2010 SDK&请参阅报告数据库架构。

http:/ /www.microsoft.com/download/en/details.aspx?id=15511
$


请参阅以下msdn文章中的更多信息:

http://msdn.microsoft.com/en-us/ library / ee767700.aspx  

http://office.microsoft.com/en-us/project-server-help/health-task-field-HA010371117.aspx



例如:关于视图,其中包含项目 健康信息

MSPLT_Health_UserView

项目健康状况:默认值是按计划,延迟,早期,阻止,完成,未指定。

Hi Arun,

Yes, You have information available in Reporting database. Project estimated Cost will be calculated based on the Assiged work* Resource rate. Actaul cost will be based on actual work & resource rates plus some other factors like material/cost resources. Project risks & issues are based on the issues/risks cretaed in project workspace.

Project server & professional has a complex scheduling engine which does all the calculations. You have options in MS project for auto-calculation on/off.

Almost all of the information is available in Projects erver reporting database. I would suggest to downlaod the Projects erver 2010 SDK & see the reporting database schema.
http://www.microsoft.com/download/en/details.aspx?id=15511

Please see more information in below msdn article:
http://msdn.microsoft.com/en-us/library/ee767700.aspx 
http://office.microsoft.com/en-us/project-server-help/health-task-field-HA010371117.aspx

e.g: About the Views, which contains the project health information
MSPLT_Health_UserView
Project Health: Default values are On Schedule, Late, Early, Blocked, Completed, Not Specified.

希望有所帮助。


这篇关于Project Server 2010项目状态自定义字段的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!