资源加载 - 配置可变船员大小和任务 [英] Resource Loading - Configuring Variable Crew Sizes and Tasks

查看:70
本文介绍了资源加载 - 配置可变船员大小和任务的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

好的, 

所以我无法找到让MS Project允许我匿名的方法船员资源(基于技能),通过所需的大量资源来定义任务(如果我可以手动更改工作量并描绘其使用的持续时间
,那么工作量将会起作用)并将资源加载到有效的找出多余工作量的方法。

So I have been unable to find a way for MS Project to allow me to make anonymous crew resources (based on skills), define tasks by a quantity of resources needed (effort driven would work if I can manually change the hrs of effort and delineate the duration it is used in) and load the resources in an effective way to find excess work loads.

例如, 

假设我们有6个装配工,4个风笛手和5个电工。

Say we have a 6 riggers, 4 pipers and 5 electricians.

根据工作的不同,我还需要2至3名机组成员。

I also have tasks for each that require 2 to 3 crew members depending on the job.

例如,我想安装一台需要的真空泵2个装配工,2个风笛手和2个电工(按照有序顺序从装配 - >管道 - >电动工作,但这不是问题.2个装配工必须一起工作,同样是
的风笛者和电工。)虽然我也有2个压力容器安装,每个需要3个装配工,2个风笛手和3个电工。

For example lets say I want to install a vacuum pump that requires 2 riggers, 2 pipers and 2 electricians (In an ordered sequence from rigging->piping->electric work, but that isn't the question here. The 2 riggers have to work together, same with the pipers and electricians.) while I also have 2 pressure vessels to install each which takes 3 riggers, 2 pipers and 3 electricians.

如何创建资源并以我不需要的方式将它们加载到任务中a)预先决定谁在做什么,以及b)允许我保持工作人员规模变量取决于他们的活动任务?

How do I create the resources and load them to the tasks in a way that I don't have to a) predetermine who works on what and b) allows me to keep the crew sizes variable dependent on their active tasks?

推荐答案

一个选项是定义通用资源并使用最大的。单位字段用于定义可用资源的数量。

An option would be to define the generic resources and use the Max. Units field to define how many resources you have available.

然后,在为单个任务分配资源时,只需使用"单位"字段再次指定特定类型需要多少资源。

Then when assigning the resources to individual tasks, just specify again using the Units field how many resources are required of a specific type.

然后MS Project将突出显示多余的工作量(分配)。

and then MS Project will highlight for you the excess work loads (overallocations).

希望这有帮助

保罗


这篇关于资源加载 - 配置可变船员大小和任务的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!