问题描述

大家好,

我目前正在使用MS Project 2010和MS Project Server 2010中的自定义交通灯字段。 目前,该字段仅在项目的时间轴级别中可见。 要查看整体项目状态,一个人可以查看项目摘要
任务。 是否可以在服务器上的项目中心级别显示相同的字段,以便有人不需要打开每个项目来查看整个项目状态? 以下是我从中提取字段
自定义的网站的链接。 

I am currently using a customized traffic light field in MS Project 2010 and MS Project Server 2010.  Currently the field is only visible in the project's timeline level.  To see the overall project status, a person can look a the Project Summary Task.  Is it possible to also show the same field at the Project Center level on the server so that someone doesn't need to open up each project to look at the overall project status?  Here is the link to the site in which I have pulled the field customization from. 

http://www.projectserverhelp.com/Lists/Posts/Post.aspx?ID=27

http://www.projectserverhelp.com/Lists/Posts/Post.aspx?ID=27

网站似乎真的很慢今天。

There website appears to be really slow today.

谢谢,

迈克

推荐答案

基本上,此公式自定义字段位于任务级别。项目中心处于项目级别,因此数据需要达到一定水平。最简单的方法是定义一个Project公式自定义字段,该字段引用您定义的任务自定义字段。
然后可以将项目自定义字段添加到项目中心视图。

Basically, this formula custom field is at the task level. Project Center is at the Project level so the data needs to come up a level. The easiest thing to do is to define a Project formula custom field that references the Task custom field you've defined. The Project custom field can then be added to a Project Center view.

希望有所帮助。

Treb Gatte,Project MVP |
@tgatte
| http://AboutMSProject.com

Treb Gatte, Project MVP | @tgatte | http://AboutMSProject.com