禁用连接项目之间的计划推送 [英] Disable schedule push between connected projects

查看:62
本文介绍了禁用连接项目之间的计划推送的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

大家好,

我遇到以下问题:

如果项目1有任务1而项目2有任务2,任务2依赖于任务1,我希望能够更改任务1的开始/结束日期,并且不会自动更改任务2的开始/结束日期,但仍然显示相互依赖关系。 

If project 1 has task 1 and project 2 has task 2, with task 2 being dependent on task 1, I want to be able to change task 1’s start/end dates and have it NOT automatically change task 2’s start/end date but still show the inter dependency. 

关于如何做到这一点的任何想法?我不能简单地将任务更改为手动安排,由于资源等其他因素,他们仍需要自动执行。

Any ideas on how to do this? I cannot simply change the tasks to manually scheduled they still need to be automatic due to other factors such as resources and such.

谢谢你们很高兴加入这个社区,

Thanks in advanced and glad to join this community,

肯特




推荐答案

嗨肯特,

您使用的是哪个项目版本?

Which Project version are you using?

首先,如果你的使用Project Server 2010,我建议您使用称为"delivrables-dependencies"的开箱即用功能。为了在项目之间链接任务。请注意,在这种情况下,您需要在发布项目计划时配置Sharepoint项目站点

First of all, if your using Project Server 2010, I'd advice you to use the out-of-the-box feature called "delivrables-dependencies" in order to link tasks among projects. Notice that in this case, you need to provision Sharepoint project sites when publishing the project plan.

您可以在此处找到信息:

You'll find information here:

http://blogs.msdn.com/b/project/archive/ 2007/02/24 / deliverables.aspx

如果你正在使用PS2003,PS2007和PS2010中已有的更基本的功能,你将能够进入高级选项对话框(menu file \options),在"inter projects链接选项"中。 (不确定翻译,我用
得到PS 2010法语..)禁用外部数据的自动更新。

If you're using the more basic functionality already available in PS2003, PS2007 and still in PS2010, you'll be able in the advanced option dialog box (menu file\options), in the "inter projects links options" (not sure of the translation, I've got PS 2010 in french..) to disable automatic updates from external data.

此外,在您的项目计划中,在"项目"中,选项卡,您可以编辑项目间链接对话框以查看所有外部依赖项并接受或拒绝任何更新。

Moreover, in your project plan, in the "project" tab, you can edit interprojects link dialog box to view all external dependencies and accept or refuse any updated.

希望这会有所帮助。


这篇关于禁用连接项目之间的计划推送的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!