Project Server(Office 365):无法修改0小时实际工作的时间表 - 错误或“功能” [英] Project Server (Office 365): timesheet with 0 hours actual work cannot be modified - bug or "feature"
问题描述
我们的一位PM正在尝试更改项目计划中的任务并收到以下消息:"无法删除或重新分配受保护的任务或作业报表" ;, 。这通常是正常的,因为我们已经通过时间表设置实际工作仅报告
但是....当检查此任务的实际工作时,只分配了1个资源并且他没有报告小时数。有趣的是,它在实际工作中显示0并且它不是空的(正如您所预期的那样,如果您不报告小时数)。
我们试图回忆该资源的时间表并重新提交它们(没有任何时间再次)但是那也没有用。想法好主意吗?
谢谢你
Choc
Chocob21
用户改变了"剩余工作"到0?我没有测试过,但我认为原因0显示为ÁctualWork并阻止你删除任务。
问候
Barbara
Hi,
One of our PMs is trying to change a task in his project plan and gets the following message: "cannot delete or reassign tasks or assignments with protected actuals" . This would normally be ok since we have setup actual work to be reported only through the timesheets but....when checking actual work on this task, there is only 1 resource allocated and he reported no hours. Interestingly, it shows 0 in the actual work and it's not empty (as you would expect if you dont report hours).
We tried to recall the timesheets of that resource and resubmit them (without any hours again) but that didnt work either. Idea good ideas?
Thanks
Choc
Chocob21
Hi,
has user changed "Remaining Work" to 0? I have not tested, but I assume that cause 0 displayed as Áctual Work and stops you from deleting task.
Regards
Barbara