问题描述
Project Server Admin如何适应资源成本中心本身的变化?
How would a Project Server Admin accommodate changes in the resource's cost center itself?
例如,Ken(时间表提交者)在成本中心C1记录2月时间,但随后转移到新团队,该团队于3月1日在成本中心C2。
For example, Ken (timesheet submitter) records Feb time in cost center C1, but then transfers to a new team, which is in cost center C2 on Mar 1st.
当我在资源级别更改其成本中心时,报告表明他之前的所有C1时间作为资源C2成本中心,他的所有C1时间看起来都是C2中的错误。
When I change his cost center at the resource level, reporting indicates all of his previous C1 time as a resource under the C2 cost center, and all of his C1 time looks like it's incorrectly in C2.
我正在考虑添加自定义资源字段来跟踪这些变化,但它似乎有很多额外的工作,如果已存在我可以使用的东西。
I am thinking about adding custom resource fields to track these changes, but it seems like a lot of extra work, if something already exists that I can use.
谢谢,
Marty
推荐答案
Marty,
Marty,
AFAIK,没有办法做这个OOB,因为资源字段不是'时间 - 分阶段"。
AFAIK, there is no way to do this OOB as Resource Fields are not 'time-phased'.
像你提到的'可能'替代方案可能是使用自定义字段来跟踪,更改(如生效日期,旧成本中心),然后以某种方式编写查询以考虑日期之间的旧成本中心。我个人没试过,
只是一个想法。
A 'possible' alternative, like you mentioned, could be be to use custom fields to track, the change (like Effective Date, Old Cost Center), and then somehow write a query to consider the old cost center between the dates. I have not tried this personally, just a thought.