资源成本更新 [英] Resource Cost update
问题描述
我们正处于设置MS Project Server 2010的过程中。我发现我的一些资源没有设置标准或加班成本 - 但是在他们输入时间表之前我没有进行发现并批准。现在我有一个数字
的任务,有几个小时的应用,但显示$ 0成本。我已经回去并更新了资源成本。如何更新任务成本?
We are just in the process of setting up MS Project Server 2010. I discovered several of my resources did not have a standard or overtime cost set up - but I did not make the discovery until after they had timesheets entered and approved. Now I have a number of tasks that have hours applied, but show $0 cost. I have gone back and updated the resource costs. How do I get the task costs to update?
感谢您的帮助,
Mike Ernst
Mike Ernst
推荐答案
需要重新发布所有适用的项目计划,以便能够查看PWA中的费用。
All the applicable project plans need to be re-published to be able to view the costs in PWA.
在项目专业人士中,这些应在您打开计划时自动计算。
In project professional, these should be calculated automatically when you open the plan.
这篇关于资源成本更新的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!