MS Project Server 2010 RDB最新基准 [英] MS Project Server 2010 RDB Most Recent Baseline
本文介绍了MS Project Server 2010 RDB最新基准的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!
问题描述
Project Server RDB中是否有一个字段用于任务级别的最新基线?
Is there a field in the Project Server RDB for the most recent baseline at a task level?
我看到的所有内容是BaselineStart0,1,2等...我正在准备一个目标报告来显示方差(我看到),但是希望将实际任务开始/结束放在与之对应的基线旁边。我是否必须写一个冗长的代码才能得到这个?
All I see is the BaselineStart0, 1, 2, etc... I'm preparing a Target Report to show the variance (which i see) but want to put the actual task start/finish next to the baseline corresponding to it. Will i have to write a lengthy code to get this?
推荐答案
不,没有"最近的基线",只有你看过的基线0-10。 其中任何一个都可能是最新的。 甚至定义业务规则来决定什么构成"最近的"构成。基线可能具有挑战性。
No, there is not a "most recent baseline," only Baselines 0-10 as you've seen. Any one of them could be the most recent. Even defining a business rule to decide what constitutes the "most recent" baseline could be challenging.
这篇关于MS Project Server 2010 RDB最新基准的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!
查看全文