Project Server 2013:将“企业资源”从“材料”修改为“工作”类型 [英] Project Server 2013: Modify an Enterprise Resource from Material to Work type

查看:73
本文介绍了Project Server 2013:将“企业资源”从“材料”修改为“工作”类型的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧!

问题描述

我有一个企业资源需要从"材料类型"更改为"工作类型"。在PWA中我没有看到这样做的选项。当我通过Project Pro 2013编辑资源时,我能够进行更改。但是,当我单击"保存"时,将打开"导入资源
向导(错误保存资源)",并显示文本"发生内部错误"。我该怎么做才能改变类型?我是否需要删除此资源并使用正确的类型输入?

I have an enterprise resource that I need to change from the Material Type to the Work Type. I don't see an option to do this in PWA. When I edit the resource through Project Pro 2013, I am able to make the change. BUT, when I click Save, an Import Resource Wizard (Errors Saving Resources) opens with the text "An internal error occurred." What can I do to change the Type? Do I need to delete this Resource and input it with the correct Type?

推荐答案

我不确定这是否可行,说实话。 您可以尝试从资源池中检出资源并在Pro ....中进行编辑,但即便如此,您最好删除旧资源并创建一个新资源。
I'm not sure this is possible, to be honest.  You could try by checking out the resource from the Resource Pool and editing in Pro....but even then you may be better to delete the old one and create a new one.


这篇关于Project Server 2013:将“企业资源”从“材料”修改为“工作”类型的文章就介绍到这了,希望我们推荐的答案对大家有所帮助,也希望大家多多支持IT屋!