Project 2010 Sub Task没有任何计划冲突 [英] Project 2010 Sub Task do not have any scheduling conflicts
问题描述
下午,
我创建了一个"主人"项目计划并包含2个项目计划作为子项目。 我遇到的问题是,虽然每个项目中的时间表冲突都没有看到彼此冲突。
I have created a "master" project plan and have included 2 project plans as sub projects. The problem I have is whilst schedules conflict within each project they are not seeing conflicts with each other.
例如,如果我在8月1日的项目A中有任务,则持续一天我在8月1日的B项目中也有一个任务,持续一天,都被分配给同一个人,两个项目都没有冲突。
For example, if I have a task in Project A on the 1st August that lasts a day and I have a task in Project B also on the 1st August that lasts for a day, both assigned to the same person, neither project shows a conflict.
我怎样才能得到2个项目要检查彼此之间的冲突吗?
How can I get the 2 projects to be checking for conflicts with each other?
谢谢
Martin
推荐答案
Hello Martin,
Hello Martin,
项目不会假设两个项目文件包含相同的资源,除非你明确告诉它,但使用资源池。 如果您查看主项目中的资源表,您将看到列出的每个项目的资源 - 您将
查看每个资源的两个条目。
Project will not assume that two project files contain the same resources unless you explicitly tell it so but using a resource pool. If you look at your resource sheet in the master project you'll see the resources from each project listed - you'll see two entries for each resource.
为了查看创建资源池文件所需的多个项目文件中的资源冲突。 幸运的是,这是相当直接的。 请参阅:
In order to view resource conflicts across multiple project files you'll need to create a resource pool file. Fortunately, it is fairly straight forward. See:
http://office.microsoft.com/en-us/project-help/share-resources-using-a-resource-pool-HA010214871.aspx#BM2
http://office.microsoft.com/en-us/project-help/share-resources-using-a-resource-pool-HA010214871.aspx#BM2
让你入门。 指示适用于2010年之前的版本。 如果您使用的是Project 2010或2013 - 您将在资源功能区上找到资源池的命令。
To get you started. The directions are for pre-2010 release. If you are using Project 2010 or 2013 - you'll find the command for resource pools on the Resource ribbon.