问题描述

大家好,
我有一个如下所述的场景.

我们创建了一个工具,用于在其中创建发布站点和发布子站点.

现在,我们创建了一个内容中心,在其中创建了我们自己的内容类型(文档)并为该内容类型定义了保留策略.

现在问题如下所示:

只要达到保留期限,工作流(SPD 2010工作流)就会从网站集级别开始,而不是在子网站级别开始.

当我们看到工作流程"屏幕时,将显示关联,但永远不会触发工作流程.

注意:我们已在全球范围内发布了工作流程.

任何帮助将不胜感激.

Hi All,
I have a scenerio described below.

We have created a tool which creates a Publishing Site and a Publishing Subsite within it.

Now we a Content hub in which we have created our own content type(Document) and defined retention policy for that content type.

Now The problem is stated below :

Whenever the retention stae is reached the Workflow (SPD 2010 Workflow)gets started on the Site collection Level but not at the Subsite level.

When we see the Workflow screen the associations are shown but the workflow is never triggered.

Note : We have published the workflow globally.

Any Help would be appreciated.

推荐答案

问题是新站点的时区设置
The problem was the time zone setting of the new site